Metro-2B Corridor Work Hits A Roadblock

Metro-2B Corridor Work Hits A Roadblock

Seven months after floating bids for construction of DN Nagar-Mandale Metro-2B corridor, the Mumbai Metropolitan Region Development Authority (MMRDA) has hit a roadblock with the corridor still lacking a crucial nod from the Airport Authority of India (AAI).

The elevated Metro corridor will run parallel to funnel zone of the Juhu aerodrome. Due to this, the height of the elevated Metro-2B will have to alter as the Juhu aerodrome consists of an emergency runway. It is also one of the busiest heliports in the country.

According to MMRDA officials, it is the AAI nod that will be crucial for commencing civil construction work on Metro-2B corridor. Funnel zone is an area where there are height restrictions and where construction of more than four storeys is not permitted. Read More…